A Jola partner specialising in IT support required a PSTN replacement solution for their customer. The project involved replacing lift lines in over 100 office buildings across the UK.
The Challenge
The partner needed a flexible solution that could be tailored to meet the needs of each site, depending on the number of lift lines required and if a Leased Line was already in place. The replacement solution had to be reliable and active 24/7, even during a power cut and comply with lift safety regulations; EN 81-28 and AS1735.
The Jola Solution
The Jola partner utilised the PSTN Toolkit to find solutions to fit the different requirements at each office building.
Each site has a router with in-built battery backup, MultiNet 4G connectivity and an auto-configured Jola ATA (Analogue Telephone Adaptor). The solution meets compliance regulations. The Jola team was available at each stage of the project, from quoting to building the solution.